INFORMED SOURCES e-Preview Special Bulletin
Due to a communications error, the schedule of IEP East Coast deliveries referred to in the March 2010 Informed Sources (page 28) was omitted from the text.
While the Table will be repeated the next time I write about IEP, I thought that e-Preview subscribers would like to have this copy below for reference while reading the item.
Delivery
Package
route
Train
Diagrams
Planned Vehicles
Start
Finish
Service
P0
ECML IC125 replacement
Bi-mode 10 car
11
130
July 2012
June 2013
May 2014(1)
P!
ECML stoppers/GN
Electric & bi-mode 5 car
22
120
December 2015
July 2016
December 2016
P5 (option)
ECML IC225 replacement (2)
Electric 10 car
n/a
n/a
2017
August 2018
2018
1) Date for completion of acceptance testing